NYCP Case Against Agency Failures to Deal With Beach Erosion ] Beach Zone Critique ] The Facts Please ] Reply to FINS ] Building Boom? ] Building Moratorium? ] [ DOI's Authority? ] Non-Struc Solutions ] FIIP Needed ] Dunesguard 2001 ] NY Times Article ]

 

Comments on Interior Department FIIP Submission on the EIS

 

Introduction

The following observations relate to comments made in a February 29 letter from the Regional Environmental Officer of the U.S. Department of the Interior (DOI) to the New York District Engineer of the US Army Corps of Engineers.  The Department listed ten major issues that it sees as preventing an endorsement of the Corps' recommended interim beach nourishment project for Fire Island.  In general, the DOI comments lack substance and balance and reflect extreme prejudice against an economically justified, soundly engineered and environmentally benign project.

The boldface headings that follow are those of the Department.  The observations are those of the Fire Island Association, a volunteer organization of more than 1,600 families and businesses on Fire Island.

 

1.  The DEIS has not satisfied NEPA's requirements to identify reasonable alternatives to the preferred alternative and evaluate those alternatives.  

The first of DOI's 10 points asserts that the DEIS fails to present a reasonable alternative to the project.  DOI would prefer an alternative that would (a) utilize the state Coastal Erosion Hazard Area (CEHA) definition of dunes as the project area; (b) incor-porate legal assurance that no increased development will occur within the dune area; and (c) entail no construction of [a] dune except, apparently, where a dune already exists.   DOI further alleges that the proposed alternatives are "inconsistent with the Congressional scheme for the Fire Island National Seashore, which is to preserve dune features and ultimately to eliminate dunefront construction through acquisition and zoning controls." (Emphasis added.) 

            There is no such "Congressional scheme."  Under the guise of seeking “reasonable alternatives,” the report writer would shift DOI's responsibility for land-use matters at the Fire Island National Seashore (FINS) to the Corps of Engineers, and thus hold the project hostage on a matter that should be resolved without reference to the latter agency. 

Regulation of construction in Fire Island's dune areas was established with the implementation of Article 34 of the state's Environmental Conservation Law (Ch. 841, Laws of 1981).  Regulations promulgated under this statute (6 NYCRR, Part 505) makes unbuildable all land southerly of a line drawn 25 feet landward of the primary dune that is augmented or newly constructed by the project, the Coastal Erosion Hazard Area, or CEHA.  This new law places large numbers of previously developed building sites off-limits to construction.  For example, in Kismet, Saltaire and Fair Harbor, the three westerly Fire Island communities, more than 150 once-developed parcels have been eliminated by unchecked erosion.  The parcels are now in the sea or on the unprotected beach.  The communities have not suggested that any of these former parcels be made usable.  To the contrary, most believe a new primary dune, kept free of new construction and augmented by regular beach nourishment, would provide protection to the communities and keep the barrier island intact.  Instead of seeking a constructive dialogue based on the communities’ reasoned and future-oriented approach to erosion control, the DOI report writer attempts instead to foist off on the Corps of Engineers DOI's own responsibility to deal with the communities on land-use issues.  In the process, he demonstrates contempt for the Corps' engineering expertise and disdain for the communities’ feeble attempts to secure protection through beach scraping, sand fencing, grass planting, and other self-help measures.  (See FIA's White Paper, "The Fire Island Interim Project Will Not Cause Building on the Dunes," April 2000.)

Under NEPA, the scope of alternatives to be considered in detail is limited to those that will achieve the underlying purposes of the project City of Alexandria v. Slater, 198 F.3d.862 (D.C.Cir. Dec.17, 1999).  Here, the project purpose is “to alleviate conditions conducive to the threat of storm damages in the study area by providing temporary storm damage protection until the findings of the Reformulation Study are available and more permanent protection can be implemented, if necessary.”  DEIS at 1-2.  The DOI comments propose alternatives that have nothing to do with the underlying purpose of the interim project. The DOI's main intent is, clearly, to remove all homes along the oceanfront.  Indeed, the Draft Decision Document states that “the NPS has identified this plan [to acquire the estimated 380 properties located within the CEHA] as their long term plan.” (DDD p. 63)  But that is not an option available to the Department.  While the agencies may wish to consider the efficacy of the DOI’s suggestions during the Reformulation Study, they do not constitute a reasonable alternative for NEPA analysis purposes of an interim project. The DOI report improperly seeks to force the Corps to adopt DOI's long-term agenda regarding property acquisition, despite the fact that it the agenda is not related to what the Corps is charged with accomplishing.  Moreover, it is unjust and unprofessional for DOI to continue to delay decisions on a project designed to address severe erosion resulting from human caused actions that have prevented the natural sand nourishment of Fire Island beaches for more than three decades.   

            Protection of those beaches is consistent with the Congressional intent of maintaining Fire Island for the use and enjoyment of future generations.  DOI’s focus on increased land acquisition goes far beyond the structure of the zoning scheme contemplated for the FINS, which is based on maintenance of the status quo with respect to private property, and restricting condemnation to limited circumstances.  (See Pub. Law No. 98- 482 limiting the authority of the Secretary to condemn and directing the Secretary to establish new guidelines to govern zoning in a manner that “reconciles the population density of the Seashore on October 17, 1984 with resource protection.”  130 Cong. Rec. 28853.)  The FIIP should not serve as a means to upset the delicate balance crafted by Congress when it created the Fire Island National Seashore. 

            Nor is it the province of the Corps of Engineers to intervene in the mutual accommodation between property owners and DOI that was inherent in the establishment of the FINS.  If there are problems arising from unchecked erosion, DOI ought first to address such issues in cooperation with the Corps and New York’s Department of Environmental Conservation, as mandated by the Fire Island National Seashore Act, 16 U.S.C § 459e-7.   Then it should engage the property owners in constructive dialogue about how to deal with repetitive losses, post-storm reconstruction issues, zoning matters, and other points of mutual interest.  Unfortunately, DOI has instead chosen to use the FIIP NEPA process as a means to force concessions on issues unrelated to the project purpose of interim storm damage protection. 

In essence, DOI views the FIIP as an opportunity to secure funding to eliminate all homes along the oceanfront, even though it has not sought funds for this purpose from Congress, and has ignored promising ways to deal with development issues on a long term basis.  While some measures were not given full consideration, as they would not be consistent with the short-term nature of an interim project, the Corps' Draft Decision Document noted a variety of measures that can be used at a later date.  These include land exchanges, land donations for tax benefits, and conservation easements with tax abatement for a period long enough to determine whether a parcel will ever again be buildable, among other things.   Consideration of this approach would, of course, require closer coordination with municipal zoning authorities, County and State governments and the property owners than has heretofore been evident.

            At the same time, none of these activities is for the Corps of Engineers to lead.  DOI cannot escape its responsibilities for land-use by insisting that the relatively well- funded Corps do the things DOI is charged with doing.  DOI must first see to it that the intention of Congress is carried out with respect to working with the island property owners.  It can’t avoid this responsibility by pleading that it lacks the funds and staff to deal with the problems confronting it, nor by foisting off the land-use obligations to a sister agency that is charged with different responsibilities.  Thus, even if  “preventing future development” is a sound “alternative” to a long-term program of protecting the shoreline, it is not an alternative that is properly the subject of a limited project of short duration.

 

2.      The DEIS does not adequately justify or explain the need for the project.  

Comment 2 alleges that "debatable interpretations of the coastal threat to the area are based on a limited database."  The analyst notes that

"The role of existing inlets in causing flood damage to the

estuarine shore is not quantifiably separated from overwash." 

[This is perhaps because there is no quantifiable overwash.]

 "Major reliance upon computer models is used to assess

implications in the future, which are not well discussed as to

their acceptance levels versus ambivalence in producing precise

values for important estimators."

It is small wonder that the Corps sometimes throws up its hands at the prospect of trying to respond to such comments.

             This comment clearly demonstrates that DOI’s critique goes well beyond the scope of the agency’s expertise and its assigned role.  Both the FINS enabling legislation and the FINS General Management Plan require that NPS rely on the Corps of Engineers' expertise in determining the appropriateness of different erosion control measures.  See 16 U.S.C. § 459e (7(a); GMP at 33.  DOI's analyst, however, sees fit to question the Corps' detailed, scientific analysis. Instead, he sets up a philosophical “difference of opinion” over the need for sand nourishment in a hairsplitting attack on minutiae of the voluminous data presented by the Corps.  The attack is unwarranted, unsupported by any countervailing information, and in no way mounts a substantive challenge the cost benefit analysis that provides the economic justification for the interim project.  The Corps used accepted methods for determining NED benefits and supported it with detailed, quantifiable data in coming up with a 1.3 C/B number.  DOI’s broadside attack on this carefully developed calculation is obviously aimed at delaying implementation of the project.

               DOI may not substitute its own views of the scientific and technical situation for that of the agency charged with making the determination.  As a commenting agency, DOI should focus on those areas relevant to its purview; namely, environmental matters related to endangered species and issues related to the operation of the Fire Island National Seashore.  Its uninformed comments on engineering, geologic and technical matters do not contribute meaningfully to the Corps' decision on whether a beach nourishment project is needed, much less how it should be designed.  Thus, when DOI says that the Corps' arguments in favor of the project are not "adequately explained," it should be remembered that it is for the Corps, not the DOI analyst, to estimate whether a breach is likely, and how to deal with the situation if it is.  Similarly, the fact that "beaches have grown larger in many areas over the past ten years" does not gainsay the fact that it has narrowed in others, nor alleviate concern about the diminution of the overall volume of sand that makes up the barrier between the Atlantic Ocean and the south shore of Long Island.

            The DOI analyst tries to minimize the need for the project by downplaying the likelihood of a breach, noting that it "is low for most of the project area.”  But he fails to mention that the Corps pointed out two areas that are prime candidates for breaching were not allowed to be included in the project: Old Inlet and Talisman/Barrett Beach.  While he notes that “Fire Island has not been breached in historic times, and that the beach has grown larger in many areas in the last ten years” he does not mention that many other areas have become smaller for lack of sand.

Putting aside the fact that DOI has exceeded the scope of its agency expertise, it has not provided any convincing evidence to refute the Corps' extensive analysis of the problem, nor called into question the efficacy of its proposed solution; i.e., the interim project.  Of course, a determined opponent who examines the data long enough is likely to discover some perceived shortcoming, but this does not mean that the Corps has not done a more than adequate job of analyzing the problem and solution.  NEPA does not demand perfection through an endless round of studies before an agency may act. 

 

3.  The project as proposed will result in adverse environmental impacts.  

The potential adverse environmental impacts the DOI analyst sees are related to backbay habitat and sea life in the project area.  The Environmental Protection Agency (EPA), however, reviewed the project and found no objection to it based on environmental or other concerns.  EPA’s letter to the Corps concluded that the project “will not only protect existing habitats for two federally threatened species … within the study area but may include designs to create habitats that are favorable to the Piping Plover … [and the project] will not cause a significant direct or indirect adverse impact (or contribute to a significant cumulative impact) to offshore borrow area habitats, and will not cause significant impacts to air quality, water quality, or wetlands.”  (1/28/00 letter from Robert W. Hargrove, Chief, Strategic Planning and Multi-Media Programs Branch, EPA Region 2 to Frank L. Santomauro, Chief, Planning Division Corps of Engineers N.Y District)  As required by its internal guidelines (see EPA, "Policy and Procedures for the Review of Federal Actions Impacting the Environment," October 3, 1984), in performing its review, EPA utilized its environmental expertise to determine whether the action agency articulated and documented the reasoning that supports its decision, analyzed data concerning the potential impacts of the proposed action on the environment and human health, and determined that a reasonable effort was made to inform and involve the public in the EIS development process.   Again, EPA’s analysis is unequivocal in its view that the environmental impacts of the FIIP are minimal.  

          DOI's analyst, however, is cavalier in addressing “environmental impacts.”  For example, he blandly states that breaches and overwashes are good, apparently because they are "natural."  In fact, however, the overall situation is decidedly unnatural.  The barrier island system inlets have been long since been stabilized, thereby removing the hydrological forces that would cause new inlets to open and existing ones to close.  Breaches caused by the effect of the Westhampton groins were closed before the existing Moriches Inlet could fill with sand.  (It is far cheaper to maintain an existing inlet than to build the structures needed to stabilize a new one.)  Given the unnatural conditions that have existed since the present inlet was stabilized and the Westhampton groinfield constructed, the only way to achieve the overwash conditions DOI finds desirable is to create them artificially.  The Corps is perfectly capable and willing to do this (see comment 9 below).  Indeed, the FINS enabling legislation contemplates DOI contributing land on which new inlets can be created when needed to adjust salinity levels in Great South Bay. 16 U.S.C. § 459e-7(b)

             Nor is DOI's insistence that the present highly erosional situation is “natural” supported by the known coastal science.  The Corps has not admitted that earlier decisions at Westhampton (where groinfield compartments were not filled and sand was not regularly bypassed at inlets because of local funding problems), materially contributed to present day erosion rates on Fire Island (see Comment 7 below).  Regardless of what happened there, and why, the Corps has an obligation to explain the impact of man's actions on Fire Island erosion rates.  It has conducted extensive studies of the subject but has so far not characterized the results in terms that can be understood either to support or reject the concept that man's actions are in part responsible for erosion of the barrier island system.  At the same time, there is no evidence to support, and EPA’s letter contradicts, DOI's contention that sea life would be permanently and significantly affected by the project, or that development in dune areas is a leading cause of erosion.  The inconsistency that erosion is "natural" on the one hand and that it is caused by dune development on the other to one side, there is evidence that contradicts the first theory and none to support the second.

             As for "negative" effects on "quality of life for residents and visitors," the need to nourish the beaches of Fire Island is well known to beachfront property owners.  As for visitors (as well as wildlife), there is ample evidence that both much prefer wide beaches to narrow ones.  Moreover, restoration of the beaches is consistent with the mandate of increasing public recreational access.

 

4.  The DEIS fails to adequately provide for the mitigation of environmental impacts.  

DOI ignores the substantial mitigation measures identified in the DEIS. See DEIS at 4-105 to 4-111 (Project Minimization Measures). The list of measures to be implemented is consistent with the notion that the agency shall adopt “all practicable means to avoid or minimize harm from the alternative selected.  40 CFR §1505.2 (c)  The DEIS also includes substantial monitoring and enforcement measures for such mitigation.  EPA obviously found this program to be reasonable when it rated the project as LO-1 and stated that the project will not result in “significant adverse environmental impacts.” (See 1/28/2000 letter from Robert Hargrove, supra p. 5)  Since the release of the DEIS, the Corps has been energetic and supportive in the area of habitat enhancement via "environmental features" of the project.  In this connection, at February 10 and May 4, 2000 meetings with the National Park Service, Fish & Wildlife Service, and state and county wildlife experts, the Corps described in detail what can be accomplished along these lines in various reaches of the interim project, and how Corps activities can contribute.

            DOI further strains credibility when it evinces concern about the lack of mitigation measures for the effect of construction activities.  Equipment is unlikely to permanently harm a beach or the invertebrate colonies on it.  For example, a moment’s reflection about DOI’s concern for “silt and shells on the beach” as a result of sand pumping would lead most to conclude that the silt will be washed away in the first rains, and shells quickly pulverized and mixed with sand.  Moreover, as demonstrated in the Westhampton project, piping plovers are unaffected by the presence of silt and shells and may even prefer such habitat.  The DOI analyst may find comfort in such simplistic concepts, but it is a stretch to find in them reasons why the project should not go forward.

 

5.  The baseline conditions in the project area are inadequately described, limiting the predictive ability of the impact analyses.  

In fact, the “baseline conditions” described in the DEIS are sufficient in terms of meeting the Corps' NEPA responsibility.  DOI has engaged in a strategy of delaying the project and then expressing concern that study data is outdated.  NEPA does not require, however, that the Corps engage in an unending cycle of updating data that has already been gathered.  The Corps has indicated that certain studies related to the Reformulation Study will be continued during the implementation of the Interim Project.  These include on-going and planned fisheries and invertebrate studies, see DEIS at 3-48, as well as studies that are related to further defining the relevant baseline and impact analysis for the barrier and backbay environments of the south shore of Long Island, see DEIS at 3-73 to 3-74.  However, the baseline for the Interim Project set out in Section 3 of the DEIS is based on a substantial amount of data and environmental studies.  The discussion of the Affected Environment is consistent with the level of detail required by NEPA, which requires that the EIS “succinctly describe the environment of the areas to be affected . . . by the alternatives under consideration.”  40 C.F.R. § 1502.15.  Again, EPA did not call this issue into question. 

 

6.  The Draft Decision Document does not accurately reference or comply with the Fire Island National Seashore General Management Plan.  

While quick to criticize the Corps for referencing older scientific studies, DOI itself does not hesitate to invoke a 22-year old General Management Plan as a basis for opposing the project.  While the region surrounding the Fire Island National Seashore has undergone immense growth and change, DOI has not seen fit to reexamine how the park should change as well.  If the Corps plan is “not consistent with” NPS plans for the FINS perhaps it is because no such plans have been articulated for over two decades.

            That said, the Interim Project is consistent with the Resources Management provisions of the GMP.  A core management objective of the GMP is “[t]o manage Fire Island in ways that will enhance natural processes and mitigate the impacts of human interference with these processes.”  GMP at 24  This is exactly what the Interim Project will accomplish.  The GMP makes it clear that DOI will rely on the Corps' expertise in determining the appropriateness of different erosion control measures.  GMP at 32  Now that the Corps seeks to exercise this expertise, the DOI analyst questions it.

            In fact, any reasonable analysis of the 1977 GMP would conclude that Interior, not the Corps, would ignore its clear mandates.  For example, the GMP clearly recognized the “unnatural” impact of man’s activities on the erosion at Fire Island: “Interruption of the littoral drift has played a major role in the acceleration of erosion of Fire Island’s beaches.”  GMP at 30  To remedy this impact, the GMP states that “Ocean -facing dunes will be repaired or restored as needed.  Planting with native, perennial dune stabilizing species to encourage revegetation will be initiated throughout the seashore.”  GMP at 33  While Interior chooses to ignore this language, the sound practicality of the plan's directive that the National Park Service take action to repair dune damage was evident in 1977, and is even more evident today.  Since nothing has been done, the damage to Fire Island’s shoreline from man induced erosion has increased over the past 20 years, and the loss to property and infrastructure that the GMP envisioned in 1977 has come to pass.  The Department’s attempt to hide behind an erroneous interpretation of the GMP should be recognized as simply another excuse to delay or kill this vital project.   

 

7.  The proposed design plan for Design Reaches 2 and 3 inconsistent with NEPA and incompatible with National Park Service Policy on sand replenishment.  

DOI believes “configuring the dune around and south of existing development will encourage increased development.”  The location of a beach fill project that must be economically justified is largely dictated by cost factors.  The trade-off is between sand and real estate.  It is sometimes cheaper to increase the amount of sand to achieve the design standard than to buy functioning beach houses and then locating the project where the houses had been.  While it is easy for non-engineers to suggest how the project could be “jogged” in this or that direction to accomplish goals ancillary to the shore protection objective, complex engineering decisions may have to made before doing so.  While such decisions must be left to the Corps, in fairness the Corps should do a better job of explaining some of the considerations that go into locating the project in one place rather than another.  When each agency tries to accommodate the others’ institutional needs, questions like this may be easily settled.

            The DEIS Problem Identification section states that, “problems encountered in the  FIIP study area consist of the loss of sand fronting the populated areas due to storm-induced erosion, and the deterioration of the natural protective features and consequent storm damage to structures in Long Island’s bay shore communities.”  DEIS at 1-2.  DOI criticizes the Corps because this section does not “indicate any human-caused event that needs to be rectified.”  But few still question whether incomplete construction of the Westhampton groinfield, failure to fill its compartments during that construction, and failure to implement regular sand bypassing at Moriches Inlet, did not contributed to depriving Fire Island of sand for the past 35 years.

            The position taken by the DOI analyst is cynical, because he knows the Corps must argue that the Westhampton groinfield and the Moriches Inlet jetties, both Corps projects, do not cause erosion effects in central and western Fire Island.  For its part, the Corps' "argument" must ignore the fact that the groinfield compartments were not filled, which prevented millions of cubic yards of sand from moving west to Fire Island.  Then, when the project was abandoned, the downdrift scour effect caused breaches in the Westhampton spit in 1981 and 1993, as the Corps predicted.  More millions of cubic yards of sand entered the bay, further depriving downdrift beaches of westerly sand flow.

Fortunately, there are signs that the Moriches Inlet ebb delta is finally reattaching to the barrier west of the inlet.  There are also grounds for optimism that the modification of the groinfield and implementation of regular bypassing at Moriches Inlet will do much to restore the natural westward flow of sand.  Still, for the Corps to admit that failure to modify the groins earlier, to ensure that groinfield compartments were filled with sand, or to implement regular bypassing in the past could be construed as an admission against interest that would encourage litigation against the government.  Any resulting lawsuit would likely drag on indefinitely and be ruled moot in the end because of the corrective steps the Corps has taken.  A seasoned government analyst would should show some understanding for the Corps’ position in this regard, and not criticize the Corps for attempting to serve its government client and ultimately the public interest.

 

8.  The ACOE does not adequately address development issues in the analysis of alternatives.  

Contrary to DOI's assertion, as FIA's white paper discusses, houses, per se, have not been significant factors in dune deterioration on Fire Island.  In fact, the oft-mentioned concern of wind scouring away sand is not an important factor when plantings and sand fencing are in place.  Owners of houses along the oceanfront have done much good work in building and nourishing the dunes through beach scraping, planting, fertilizing, irrigating and fencing, and in most cases their actions have been a net plus to the resource.  Still, the existing erosion situation the Corps has been called on to address could have been avoided by a reasonable, ongoing program of beach nourishment over the years.  Indeed, placement of a replenished dune southerly of the present first row of houses in some cases, along with regular nourishment thereafter, is the only practical solution to the Fire Island erosion problem.  This does contemplate continued existence of houses near the dune area, however, plus infilling in some places.  That means it will not meet DOI's objective of removing residential construction from the beach.  That is an objective, however, that is not supported by the law or the Department's mandate for Fire Island. 

Nor is there is any legal basis upon which the Corps could require a "moratorium or other means of preventing further construction," as the DOI analyst naively "insists."  There is no provision for imposing a moratorium on construction in the community development district, either in the FINS Act or in the zoning regulations adopted for FINS in the early 1990s, see 36 C.F.R. Pt. 28.  In addition to constitutional problems under state and local law, any attempt to enact a moratorium would run counter to Congress’s intent to insure the continued viability of the Fire Island communities and respect for property rights. The notion that some 340 homes can be “relocated” is totally impractical and would lead to protracted and costly litigation.  FIA environmental counsel has reviewed the legal questions involved in a construction moratorium and prepared a detailed analysis refuting the DOI analyst's amazing statement, presented in boldface, italicized type: "Therefore, we must insist that an enforceable building moratorium be in place prior to any beach nourishment actions."  It says little for the Department's supervisory or legal review procedures that such a statement is put forth in a public document.

 

9.  The DEIS does not include specific project features that will reduce impacts to threatened and endangered species.  

DOI’s double standard on this subject is described above (Comment 4).  In brief, the Corps is able and willing to implement virtually any habitat enhancement program that DOI feels would be useful to the preservation of threatened or endangered species.  The Corps has offered to create beach overwash areas, for example, to prevent the loss of plover eggs to wave runup on certain beaches.  Instead of availing itself of this offer DOI simply continues to deplore the fact that it has not been made.  In response to Corps offers to create new or enhanced habitat for endangered species, the complaint is heard that "We can't manage the habitat we already have."  If concern about wildlife were its real concern (rather than preventing landowners' use of their property) DOI would work closely with the Corps in building the habitats needed to enhance protection and productivity of endangered wildlife.  Blocking the project, on the other hand, means narrower and lower beaches, and, in general, an environment less conducive to the species protection.

            The DOI analyst writes that, "We recommended creation of active overwash areas, clearing heavily vegetated areas, and reduction of fill placement areas as potential measures to achieve this goal [of maximizing preservation of piping plover and seabeach amaranth].  In the same section he states, "No dune grass planting, snow fencing, or other dune stabilization activities may be conducted in association with interim project features."  In one proposal he suggests destroying vegetation that exists and in another recommends no dune grass planting or fencing, the best ways known to prevent dune erosion.  This after specifying that beach nourishment should be restricted to the communities, where piping plovers, the presumed reason for the strictures, are virtually unknown.  The logic is difficult to follow.  

10.  Impacts to visitor use and recreation, and associated economic analyses, are inadequately addressed in the DEIS and DDD.

DOI’s most cynical, not to say stupid, comment in this document is the suggestion that the island itself, as well as its visitors, would be better off without a beach nourishment project than with it, because the project would entail work being done on the beach.  The Corps has successfully undertaken beach fill projects up and down the American coastline (albeit usually with the enthusiastic endorsement of state and local agencies) and a brief interference with the ability to access the beach is seldom if ever raised as a reason for not doing a project.  Moreover, the Park Service often grants permits for nourishment projects at other national seashores.  Certainly a temporary dislocation is preferable to the permanent one likely to result if the island is breached or so seriously eroded that auto and truck beach traffic is forced inland.

            Beach nourishment projects are routinely scheduled to take place in seasons away from the times beaches are most in use, and when protected bird species are courting, nesting or fledging checks.  Nor are projects so extensive in impact that beach users cannot avoid the construction activity by moving a short distance along the beach.  

CONCLUSION

            An analysis of DOI’s ten points makes it clear that the DOI objective is not the kind of interagency cooperation intended by Congress when it wrote, “shore erosion control or beach protection measures [on Fire Island] shall be exercised in accordance with a plan that is mutually acceptable to the Secretary of the Interior and the Secretary of the Army … .” 16 U.S.C. § 459e 7.  This was reiterated in the six-point agreement that the agencies entered into in June 1999.  Instead of cooperating, DOI has shown a single-minded determination to effect control of land use on the barrier island through the bureaucratic manipulation of the beach protection process.  By this it is hoped that a return to the discredited “retreat” doctrine can be effected.  If so, the policy, which is aimed at giving federal and state government greater control over local shorelines, will meet strong opposition from local government as well as property owners.  Costly and protracted litigation may well be expected to follow violation of individual property rights.

A policy of interagency cooperation and restoration of the spirit of mutual support that was the basis of the creation of the Seashore, would go far toward solving this problem to the benefit of all sides, not to mention to the general public.

Fire Island Association
May 2000


Back ] Up ] Next ]


The Fire Island Association, Inc.
P.O. Box 424 · Ocean Beach, NY 11770
212.929.6415  ·  212.929.3746  ·  info@fireislandassn.org