Browsing Uncategorized's Archives »»

The purpose of the recently constructed project was to restore protective features of the beach and dune system in Ocean Bay Park for short-term storm protection and enhance recreation.  Periodic beach nourishment is a normal maintenance activity for waterfront communities that are subjected to erosion of their beach and dune systems.  Shoreline recession coupled with the April 2007 nor’easter had resulted in critical erosion in sections of Ocean Bay Park.

The beach and dune nourishment consisted of constructing a beach berm with an elevation of 7.9 ft NAVD and a dune elevation of 13.9 ft NAVD along the community’s length of 2,281 ft.  The beach is stabilized by a taper section to the east and similar fill projects to the west. The 13.9 ft NAVD dune elevation is the same as the 15.0 ft NGVD elevation discussed in the Corps studies, but is just a newer datum.  The NAVD datum approximates mean sea level.  Dune slopes were built to be 1 ft vertical to 4 ft horizontal between the dune crest and beach berm.

The constructed beach berm was built wider than the expected equilibrium profile.  The construction profile will lose up to half its width and reach the equilibrium profile in a period of months to a year, which is demonstrated in the figure below.  The equilibrium profile will intersect the existing bottom at approximately -19 ft NAVD, which is the seaward limit of the active beach profile.

Overall, 159,000 cubic yards of sand were placed onto the project area in Ocean Bay Park.  However, only 96.7% cubic yards of the placed volume was eligible for pay.  The project area will be surveyed periodically in order to monitor the performance of the project.

2009 FIRE ISLAND, NY BEACH RENOURISHMENT
PROJECT DESCRIPTION
INTRODUCTION AND LOCATION
Eleven Fire Island communities are currently concluding a beach
renourishment project that began construction on January 27, 2009. The
eleven communities, shown below (figure 1) are part of the Towns of Islip
and Brookhaven, and the Villages of Saltaire and Ocean Beach, on Long
Island, New York.
read more from "Description — 2009 Projects"

FIA Press Release 4-17-09



For Immediate Release

Contact: Jerry Stoddard

(212) 929-6415

Homeowners and Officials Tour Fire Island Beach Projects

Ocean Beach, N.Y. April 17 — Elected and agency officials joined coastal engineers and homeowner representatives on April 17 in a tour of a beach nourishment project Fire Island homeowners hope will protect their communities.
read more from "FIA Press Release 4-17-09"

CPE’s Nicole Sharp reported late Wednesday that Ocean Bay Park’s project was completed late Tuesday. Operations moved to Seaview and west and had extended from Fairway Avenue to Crescent Avenue by Wednesday night.  The RN Weeks left early Wednesday morning for repairs and the BE Lindholm stopped pumping around noon due to rough seas. When the sea is calmer pumping will resume near the east border of the village of Ocean Beach.

FIA has arranged a tour for officials, the press and others for Friday morning, April 17. Fire Island Ferries has provided a boat to leave from Bay Shore at 9:00 a.m. The group will proceed to the beach, probably near Surfview Walk, to view the operation. Mayor Loeffler will welcome the visitors to the Village and a presentation on the beach fill techniques in use will be made by Steve Keehn, Senior Coastal Engineer for CP&E, at the Boat House in Ocean Beach. After a Q&A session, FIA president Jerry Stoddard will present certificates of appreciation to some of the government officials who helped arrange the permits and draft the contracts for the project.

The purpose of the tour is to underscore the fact that in the absence of government help, coastal residents sometimes must spend their own money to protect adjacent public beaches. But regardless of where the money comes from, for the next fifty years at least, the nation’s chief response to sea-level rise will be to make beaches wider and higher though periodic beach nourishment projects like the one now underway by Weeks Marine, Inc. at Fire island.

The FIA press release on the site visit and CP&E’s project description appear in the following posts.

Project Update 4/4/2009



Coastal Planning & Engineering’s Quin Robertson reported that pumping began in the Central Reach (Ocean Bay Park to Corneille Estates/Summer Club) around midnight on March 31. The R.N. Weeks pumped 2,300 cubic yards of sand before midnight that night and has since pumped another 85,000 yards in Seaview. There are two submerged pipelines, central and east. The central line, located between Fairway and Gale in Seaview, is currently building the beach eastward toward the border between Ocean Bay Park and Point O’Woods. The second (eastern) sub-line is located at about Oneida Street in eastern Ocean Bay Park. It is not yet in operation because winds must subside before the monobuoy (the pumping platform that connects the dredge to the submerged pipeline) can be connected. Repairs are also needed on the dredge, the B.E. Lindholm, which will serve the east sub-line when it is in place. Once this happens, the central line will help complete the eastern part of the Central Reach, and then both dredges will serve the central sub-line, building the beach toward its western completion point. Weeks Marine expects the Lindholm to be back on-line shortly, allowing double pumping of the east end of the Central Reach with two sub lines.  The eastern and central sub line will work towards each other to finish the eastern half as soon as possible.

The vehicle cut between Ocean Bay Park and Point O’Woods will remain closed until the eastern half of the Central Reach is completed. Until then, there is no driving on the beach between Ocean Beach and Ocean Bay Park except for emergency vehicles.

Project Update 3-29-09



Despite equipment problems that prevented double pumping (where both of Weeks Marine’s dredges are at work in a single location) and a last-minute onset of bad weather, the projects at Fire Island Pines and Davis Park are expected to have been successfully concluded before the date at which activity at the eastern end of the projects must end under terms of the permit.

Weeks was at work dressing both beaches (the final step before equipment removal) on Sunday. Stockpiles of sand accumulated during the final day of sand pumping will be distributed throughout the eastern ends of the reaches to maintain as equitable distribution of sand as possible. A beach project is not over until a survey is performed to determine the extent to which the dredger has delivered and placed the amount of sand agreed on. But with dressing completed, Weeks will be moving its equipment from the eastern reaches to the central reach over the next three days.

Work will begin on the central reach (the fourth and final part of the community projects) as soon as the weather is calm enough to move the sub line there from Davis Park.  Moving the sub line requires calm seas, and the contractor hopes this will occur by Tuesday. That would allow pumping in central Fire Island to begin that evening.  The dredge B.E. Lindholm, which had equipment problems, should be back in service at around the same time. Thus, double pumping can begin as soon as the sub line is installed.  The sub line now at the Pines will also be installed in the central reach to maximize efficiency (each sub line with its own dredge). This will happen during the first favorable weather window after installation of the first sub line.

With decent weather, the entire project should be completed before April 25. Following project completion, Weeks will remove all equipment by barge during the earliest window of good weather.

Thanks to Coastal Planning’s Quin Robertson, Ph. D., for the information in this report.

CPE’s Nicole Sharp reports that progress is good at Davis Park with two dredges operating there since Friday March 20. Both the RN Weeks and the BE Lindholm moved to Davis Park late Friday evening to increase the rate of beach construction. As of this afternoon, approximately 50 linear feet of beach was left to complete the western segment of Davis Park.  Weeks expects to flip the pipeline tonight and begin to fill the eastern portion of the Davis Park. Double dredge operations will continue until mid-week and then one dredge will be move back to FI Pines.  Repairs to the mono-buoy needed to pump the sand ashore in FI Pines were completed today under mild sea conditions.

Project Update



Early results of the first pumping at Davis Park can be seen in the following link:

http://www.davispark.info/Leja/Endless/031509/index5.htm

Nicole Sharp reported that on Saturday pumping on the eastern segment of FI Pines commenced early in the morning when the pipeline was flipped from the western segment.  [When the submerged pipeline brings sand onto the center of the beach, above-ground pipe directs it to one end of the project area. When that part of the project area is filled, the pipe is flipped and sand is moved to the other end. When the beach is filled, the pipe is removed and the beach is graded. -Ed.] Dredging operations were delayed for a few hours in the afternoon to make a minor repair to the subline. Final grading and dressing still needs to be done before the beach can be reopened to traffic from the West.  Currently, pumping operations are in the vicinity of Neptune Walk.  Pumping for Davis Park was expected to start Saturday night.

« Previous PageNext Page »